How to Design Reinforced Concrete
There are times where a concrete slab will have to be reinforced. You can design a reinforced slab yourself as long as you have the proper tools. Reinforced slabs can last a very long time so your family and friends will be able to enjoy it for years to come.
Things you need:
- Double headed nails
- 2-½ inch rebar rods
- Rebar wire
- 3-inch dobey bricks
- Wire mesh
- Diesel fuel
- Water hose
- Rake
- Concrete
- Sand
- Chalk line
- Shovel
- 2x10 form boards
- Level
- Hammer
- 12-inch wooden stakes
- Make a mark for the boundaries of the slab with a chalk line. This will let you know where to apply the concrete.
- Make sure you dig the footer six inches deep. The footer must be level all the way so the slab will be level as well. You can use a level to make sure the footer in leveled properly.
- Create a concrete curb to prevent concrete from escaping the slab. Take some 2x10 boards and put them around the edges or the area. The boards should be six inches above the top of the poured slab.
- Take a hammer and use it to put stakes in the ground around the perimeter of the slab. Make sure the stakes are about 12 inches apart. You will then put them against the form boards.
- Take some double headed nails and hammer them in the boards so the boards will be steady when you pour the concrete.
- Mark the slab mentally in three sections. Keep in mind that the division doesn’t have to be exact, but it has to be very close. Take some 3-inch dobey bricks and mark the lines.
- Put some wire mesh on top of the dobey bricks. Be sure that you cover the whole area that will be poured with concrete.
- Take the ½-inch rebar rods and put them on top of the wire mesh.
- Take some diesel fuel and spray the form boards. Be sure to let it dry all the way.
- Get a 2-inch layer of sand and fill the whole slab area. Next get a water hose and dampen the sand. You will then rake it to make it smooth.
- Take some more ½-inch rebar rods and make a grid in the slab area. Make sure they are 12 inches apart vertically in the area.
- Use rebar wire to tie the rods together so it doesn’t shift.
- Take the concrete and pour it inside the form boards. Let it cure for up to three days.