How to Form a Foundation Using Cement Blocks
Concrete block foundations are not difficult to build if you have average construction or home improvement skills. By using a proper block laying technique for installation, a foundation can generally be constructed in less than a week, depending on the size of the project. Here's how to get started:
Supplies
- Concrete blocks
- Mortar mix
- Hand trowel
- Level
- Thumb jointer
- Lay out the foundation walls. Be sure they are square at the corners.
- Start at one corner and run a tape along, marking your wall dimensions. This should be done for all four corners.
- Double-check the corners by measuring them diagonally. The measurements across both diagonal measurements should be the same. Make any needed adjustments and recheck the measurements.
- Pull and snap a chalk line on the footings to connect the corner marks.
- This is where you will begin laying your first row of blocks. Make sure your foundation is a height of at least 48 inches on all sides.
- Place four blocks in one direction from a corner and three blocks in the opposite direction of the corner. Apply a two inch bed of mortar using the trowel for the first row of blocks. Make sure to apply mortar where the block ends join together.
- Stagger the next row of blocks. Apply mortar to the top of each previously laid block before stacking the next block.
- Make sure to use a level to keep the corner plumb and block frame straight.
- When the blocks are laid use a thumb jointer to smooth out joints.